Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 5 The complete diagram for the following PERT problem is shown below. Activity Predecessors Optimistic Most Likely Pessimistic Expected Time (Weeks) A --- 4

Problem 5 The complete diagram for the following PERT problem is shown below. Activity Predecessors Optimistic Most Likely Pessimistic Expected Time (Weeks) A --- 4 7 10 7 B A 2 8 20 9 C A 8 12 16 12 D B 1 2 3 2 E D, C 6 8 22 10 F C 2 3 4 3 G F 2 2 2 2 H F 6 8 10 8 I E, G, H 4 8 12 8 J I 1 2 3 2 a. Determine the critical path and write the activities on the critical pathe and the completion time here. b. Compute the project standard deviation and write its value here. c. Determine the probabilitythat the project can be completed in the following time periods. i. Less than 42 weeks ii. Greater than 35 weeks iii. Between 42 to 44 weeks iii. Greater than 40 weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cases In Human Resource Management In Hospitality

Authors: Shirley Gilmore

1st Edition

0131119834, 9780131119833

More Books

Students also viewed these General Management questions

Question

How does a pension plan differ from a profit-sharing plan?

Answered: 1 week ago

Question

8. What values do you want others to associate you with?

Answered: 1 week ago