Question
Problem 5 The complete diagram for the following PERT problem is shown below. Activity Predecessors Optimistic Most Likely Pessimistic Expected Time (Weeks) A --- 4
Problem 5 The complete diagram for the following PERT problem is shown below. Activity Predecessors Optimistic Most Likely Pessimistic Expected Time (Weeks) A --- 4 7 10 7 B A 2 8 20 9 C A 8 12 16 12 D B 1 2 3 2 E D, C 6 8 22 10 F C 2 3 4 3 G F 2 2 2 2 H F 6 8 10 8 I E, G, H 4 8 12 8 J I 1 2 3 2 a. Determine the critical path and write the activities on the critical pathe and the completion time here. b. Compute the project standard deviation and write its value here. c. Determine the probabilitythat the project can be completed in the following time periods. i. Less than 42 weeks ii. Greater than 35 weeks iii. Between 42 to 44 weeks iii. Greater than 40 weeks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started