Problem 5-14 (Static) Here is a CPM network with activity times in weeks: B(5) (C(6) A(7) (G(3) (D(6) E(4) F(8) a. Determine the critical
Problem 5-14 (Static) Here is a CPM network with activity times in weeks: B(5) (C(6) A(7) (G(3) (D(6) E(4) F(8) a. Determine the critical path. A-B-C-D A-E-G-C-D A-E-F-D b. How many weeks will the project take to complete? Number of weeks b. How many weeks will the project take to complete? Number of weeks c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? Number of weeks reduced