Problem 5-39A (Part Level Submission) Stellar Stairs Co. designs and builds factory-made premium wooden stairs for homes. The manufactured stair components (spindles, risers, hangers, hand

Problem 5-39A (Part Level Submission)

Stellar Stairs Co. designs and builds factory-made premium wooden stairs for homes. The manufactured stair components (spindles, risers, hangers, hand rails) permit installation of stairs of varying lengths and widths. All are made of white oak wood. The companys budgeted manufacturing overhead costs for 2016 are as follows:

Overhead Cost Pools Amount
Purchasing $69,000
Handling materials 82,000
Production (cutting, milling, finishing) 210,000
Setting up machines 95,000
Inspecting 90,000
Inventory control (raw materials and finished goods) 126,000
Utilities 180,000
Total budget overhead costs $852,000

For the last four years, Stellar Stairs Co. has been charging overhead to products on the basis of machine hours. For 2016, it has budgeted 100,000 machine hours. Heather Fujar, owner-manager of Stellar Stairs Co., recently directed her accountant, Kiko Nishikawa, to implement the activity-based costing system that she has repeatedly proposed. At Heather Fujars request, Kiko and the production foreperson identify the following cost drivers and their usage for the previously budgeted overhead cost pools.

Activity Cost Pools Cost Drivers Expected Use of Cost Drivers
Purchasing Number of orders 600
Handling materials Number of moves 8,390
Production
(cutting, milling, finishing) Direct labour hours 102,340
Setting up machines Number of set-ups 1,740
Inspecting Number of inspections 6,320
Inventory control
(raw materials and finished goods) Number of components 170,030
Utilities Square metres occupied 10,220

Jason Dion, sales manager, has received an order for 280 stairs from Community Builders, Inc., a large housing development contractor. At Jasons request, Kiko prepares cost estimates for producing components for 280 stairways so Jason can submit a contract price per stair to Community Builders. She accumulates the following data for the production of 280 stairways:

Direct materials $103,600
Direct labour 112,000
Machine hours 14,500
Direct labour hours 5,000
Number of purchase orders 60
Number of material moves 800
Number of machine set-ups 100
Number of inspections 450
Number of components 16,000
Number of square metres occupied 800

What is the manufacturing cost per stairway under the proposed activity-based costing? (Round answer to 2 decimal places, e.g. 15.25.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And Cost Accounting Student Manual Free Tracked Delivery

Authors: Colin Drury, Mike Tayles

1st Edition

9781473773622

More Books

Students also viewed these Accounting questions