Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,184,000 $3,510,000 $2,316, 600 Estimated costs to complete as of year-end 5, 616,000 2,106,000 @ Billings during the year 2,120,000 3,574,000 4,306,000 Cash collections during the year 1,860,000 3,400,000 4,740,000 Westgate recognizes revenue over time according to percentage of completion Problem 6-10 (Algo) Part 3 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) 2021 2022 Balance Sheet(Partial) Current assets 0 0 Current Kabas Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,184,000 $3,510,000 $2,316, 600 Estimated costs to complete as of year-end 5, 616,000 2,106,000 @ Billings during the year 2,120,000 3,574,000 4,306,000 Cash collections during the year 1,860,000 3,400,000 4,740,000 Westgate recognizes revenue over time according to percentage of completion Problem 6-10 (Algo) Part 3 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) 2021 2022 Balance Sheet(Partial) Current assets 0 0 Current Kabas