Problem 7-18 Activity-Based Costing and Bidding on Jobs [LO7-2, LO7-3, LO7-4] Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings.

Problem 7-18 Activity-Based Costing and Bidding on Jobs [LO7-2, LO7-3, LO7-4]

Mercer Asbestos Removal Company removes potentially toxic asbestos insulation and related products from buildings. There has been a long-simmering dispute between the companys estimator and the work supervisors. The on-site supervisors claim that the estimators do not adequately distinguish between routine work, such as removal of asbestos insulation around heating pipes in older homes, and nonroutine work, such as removing asbestos-contaminated ceiling plaster in industrial buildings. The on-site supervisors believe that nonroutine work is far more expensive than routine work and should bear higher customer charges. The estimator sums up his position in this way: My job is to measure the area to be cleared of asbestos. As directed by top management, I simply multiply the square footage by $2.80 to determine the bid price. Since our average cost is only $2.575 per square foot, that leaves enough cushion to take care of the additional costs of nonroutine work that shows up. Besides, it is difficult to know what is routine or not routine until you actually start tearing things apart.

To shed light on this controversy, the company initiated an activity-based costing study of all of its costs. Data from the activity-based costing system follow:

Activity Cost Pool Activity Measure Total Activity
Removing asbestos Thousands of square feet 800 thousand square feet
Estimating and job setup Number of jobs 400 jobs
Working on nonroutine jobs Number of nonroutine jobs 100 nonroutine jobs
Other (organization-sustaining costs and idle capacity costs) None
Note: The 100 nonroutine jobs are included in the total of 400 jobs. Both nonroutine jobs and routine jobs require estimating and setup.

Costs for the Year
Wages and salaries $ 372,000
Disposal fees 775,000
Equipment depreciation 96,000
On-site supplies 58,000
Office expenses 280,000
Licensing and insurance 480,000
Total cost $ 2,061,000

Distribution of Resource Consumption Across Activities
Removing Asbestos Estimating and Job Setup Working on Nonroutine Jobs Other Total
Wages and salaries 60 % 10 % 20 % 10 % 100 %
Disposal fees 60 % 0 % 40 % 0 % 100 %
Equipment depreciation 50 % 10 % 15 % 25 % 100 %
On-site supplies 70 % 20 % 10 % 0 % 100 %
Office expenses 10 % 40 % 20 % 30 % 100 %
Licensing and insurance 25 % 0 % 60 % 15 % 100 %

Required:

1. Perform the first-stage allocation of costs to the activity cost pools.

2. Compute the activity rates for the activity cost pools.

3. Using the activity rates you have computed, determine the total cost and the average cost per thousand square feet of each of the following jobs according to the activity-based costing system.

a. A routine 1,000-square-foot asbestos removal job.

b. A routine 2,000-square-foot asbestos removal job.

c. A nonroutine 2,000-square-foot asbestos removal job.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advances In International Accounting Volume 20

Authors: J. Timothy Sale

1st Edition

0762313994, 9780762313990

More Books

Students also viewed these Accounting questions

Question

Understand the post-crisis debate on HRM and pedagogy

Answered: 1 week ago