Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 8-20 Complete the steps below using cell references to given data or previous calculations. In some cases, a simple cell reference is all you

image text in transcribed

Problem 8-20 Complete the steps below using cell references to given data or previous calculations. In some cases, a simple cell reference is all you need. To copy/paste a formula across a row or down a column, an absolute cell reference or a mixed cell reference may be preferred. If a specific Excel function is to be used, the directions will specify the use of that function. Do not type in numerical data into a cell or function. Instead, make a reference to the cell in which the data is found. Make your computations only in the blue cells highlighted below. In all cases, unless otherwise directed, use the earliest appearance of the data in your formulas, usually the Given Data section. You have 3 projects with the following cash flows: 0 1 2 3 4 Year Project 1 Project 2 Project 3 -$150 -$825 $20 $20 SO $40 $40 $0 $60 $60 $7,000 S80 $80 -$6,500 -$245 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project (to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20% 50%? a. For which of these projects is the IRR rule reliable? The IRR rule is reliable for b. Estimate the IRR for each project (to the nearest 1%). IRR Project 1 Project 2 Project 3 c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? 5% 20% 50% Project 1 Project 2 Project 3 Requirements 1. Start Excel - completed. 2. In cell E15, select from the dropdown for which of the projects the IRR rule is reliable (1 pt.). 3. In cell D20, by using cell references and the function IRR, calculate the internal rate of return for Project 1 (1 pt.). Note: Do not enter any value for the Guess argument of the function IRR. 4. To calculate the IRR for projects 2 and 3, copy cell D20 and paste it onto cells D21:D22 (1 pt.). 5. In cell D27, by using cell references and the function NPV, calculate the net present value of Project 1 if the cost of capital is 5% (1 pt.). 6. To calculate the net present values of projects 2 and 3 if the cost of capital is 5%, copy cell D27 and paste it onto cells D28:D29. To calculate the net present values of each project if the cost of capital is 20% and 50% respectively, copy cell D27 and paste it onto cells E27:F29 (1 pt.). 7. Save the workbook. Close the workbook and then exit Excel. Submit the workbook as directed. Problem 8-20 Complete the steps below using cell references to given data or previous calculations. In some cases, a simple cell reference is all you need. To copy/paste a formula across a row or down a column, an absolute cell reference or a mixed cell reference may be preferred. If a specific Excel function is to be used, the directions will specify the use of that function. Do not type in numerical data into a cell or function. Instead, make a reference to the cell in which the data is found. Make your computations only in the blue cells highlighted below. In all cases, unless otherwise directed, use the earliest appearance of the data in your formulas, usually the Given Data section. You have 3 projects with the following cash flows: 0 1 2 3 4 Year Project 1 Project 2 Project 3 -$150 -$825 $20 $20 SO $40 $40 $0 $60 $60 $7,000 S80 $80 -$6,500 -$245 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project (to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20% 50%? a. For which of these projects is the IRR rule reliable? The IRR rule is reliable for b. Estimate the IRR for each project (to the nearest 1%). IRR Project 1 Project 2 Project 3 c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? 5% 20% 50% Project 1 Project 2 Project 3 Requirements 1. Start Excel - completed. 2. In cell E15, select from the dropdown for which of the projects the IRR rule is reliable (1 pt.). 3. In cell D20, by using cell references and the function IRR, calculate the internal rate of return for Project 1 (1 pt.). Note: Do not enter any value for the Guess argument of the function IRR. 4. To calculate the IRR for projects 2 and 3, copy cell D20 and paste it onto cells D21:D22 (1 pt.). 5. In cell D27, by using cell references and the function NPV, calculate the net present value of Project 1 if the cost of capital is 5% (1 pt.). 6. To calculate the net present values of projects 2 and 3 if the cost of capital is 5%, copy cell D27 and paste it onto cells D28:D29. To calculate the net present values of each project if the cost of capital is 20% and 50% respectively, copy cell D27 and paste it onto cells E27:F29 (1 pt.). 7. Save the workbook. Close the workbook and then exit Excel. Submit the workbook as directed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Personal Finance For Dummies

Authors: Eric Tyson

5th Edition

0470038322, 978-0470038321

More Books

Students also viewed these Finance questions

Question

Tell the merits and demerits of Mendeleev's periodic table.

Answered: 1 week ago