Problem (a) Draw a network diagram in both AIB and AOA format that represents the development task list indicated below. Determine the earliest-latest starting and
Problem
(a) Draw a network diagram in both AIB and AOA format that represents the development task list indicated below. Determine the earliest-latest starting and finishing times for each activity, the slack for each activity, and the critical path.Assume the project starts at time zero and completion date is the earliest date possible.
Activity Immediate predecessor Time (weeks)
A -- 4
B -- 6
C A,B 7
D B 8
E B 5
F C 5
G D 7
H D,E 8
I F,G,H 4
(b) Suppose it is desired to accelerate the schedule by 2 weeks. What strategy might the company consider to make up the time (2 weeks). Explain.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started