Problem II (16 pts) On February 1, 2002, Coe Contractors agreed to construct a building at a contract price of $6,000,000. Coe estimated total construction
Problem II (16 pts)
On February 1, 2002, Coe Contractors agreed to construct a building at a contract price of $6,000,000. Coe estimated total construction costs would be $4,200,000 and the project would be finished in 2004. Information relating to the costs and billings for this contract are as follows:
2002 2003 2004
Total costs incurred to date $1,470,000 $2,695,000 $4,700,000
Estimated costs to complete 2,730,000 2,205,000 -0-
Customer billings to date 2,200,000 4,000,000 6,000,000
Collections to date 2,000,000 3,500,000 5,900,000
INSTRUCTIONS 1.Complete a schedule in good form detailing the calculation of gross profit recognized for each of years under the percentage of completion method
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started