Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem Statement - Selecting Projects for Bidding: A contractor has identified a set of eight major construction projects that are to be awarded on the

image text in transcribed
image text in transcribed
Problem Statement - Selecting Projects for Bidding: A contractor has identified a set of eight major construction projects that are to be awarded on the basis of sealed bids. The contractor is reasonably confident of being able to submit the low bid on each of the projects, but does not have the resources to undertake all of them. The projects are large in scale, and each will require different levels of labor, materials, and equipment to complete. The contractor's labor and equipment resources are limited. Each bid also requires time and special expertise to prepare, and these are limited as well. The question facing the contractor is which projects should be selected for bidding. The relevant data for each of the eight projects are presented in Table 1, including the time necessary to prepare a bid and the expected profit that would result from being awarded and completing each project. Estimates for the major resources needed for a particular project are also included. For example, project 3, the re- decking of an urban bridge crossing a major river would require a skilled labor input of about 4,000 hours and the use of a very large crane during almost the entire project. The bid for this project would be the first of its kind undertaken by this contractor, and would thus take approximately 13 person weeks to prepare. The profit resulting from being awarded and successfully completing this project is estimated to be $100,000. The resources available to the contractor for preparing bids and completing projects that might be awarded are limited. The company owns three cranes, each of which is suitable for any of the projects. Only 30,000 hours of skilled labor are expected to be available to the contractor during the period of the projects. A team of four project estimators will prepare all bids so that over the next three months, a total of only 50 person-weeks is available. Also, due to the distance between projects, project number 7 and number 8 cannot be jointly pursued. The company confidently assumes that it will win any bid that it prepares. Which projects should be pursued? 1. (35 points) Formulate the model using the five elements of a math program maximizing profit and adhering to the constraints described in the problem description above. 2. (15 points) Describe the method you would use to solve this model. Detail (but do not solve) the basic steps associated with the method and how they would relate to the problem given. Table 1: Project Requirement Data Time to prepare Project # *bid (person-weeks) Thousands of hours of skilled labor needed Crane Required? (1 = yes, 0 = no) Profit If Project Won ($1000) con m in Problem Statement - Selecting Projects for Bidding: A contractor has identified a set of eight major construction projects that are to be awarded on the basis of sealed bids. The contractor is reasonably confident of being able to submit the low bid on each of the projects, but does not have the resources to undertake all of them. The projects are large in scale, and each will require different levels of labor, materials, and equipment to complete. The contractor's labor and equipment resources are limited. Each bid also requires time and special expertise to prepare, and these are limited as well. The question facing the contractor is which projects should be selected for bidding. The relevant data for each of the eight projects are presented in Table 1, including the time necessary to prepare a bid and the expected profit that would result from being awarded and completing each project. Estimates for the major resources needed for a particular project are also included. For example, project 3, the re- decking of an urban bridge crossing a major river would require a skilled labor input of about 4,000 hours and the use of a very large crane during almost the entire project. The bid for this project would be the first of its kind undertaken by this contractor, and would thus take approximately 13 person weeks to prepare. The profit resulting from being awarded and successfully completing this project is estimated to be $100,000. The resources available to the contractor for preparing bids and completing projects that might be awarded are limited. The company owns three cranes, each of which is suitable for any of the projects. Only 30,000 hours of skilled labor are expected to be available to the contractor during the period of the projects. A team of four project estimators will prepare all bids so that over the next three months, a total of only 50 person-weeks is available. Also, due to the distance between projects, project number 7 and number 8 cannot be jointly pursued. The company confidently assumes that it will win any bid that it prepares. Which projects should be pursued? 1. (35 points) Formulate the model using the five elements of a math program maximizing profit and adhering to the constraints described in the problem description above. 2. (15 points) Describe the method you would use to solve this model. Detail (but do not solve) the basic steps associated with the method and how they would relate to the problem given. Table 1: Project Requirement Data Time to prepare Project # *bid (person-weeks) Thousands of hours of skilled labor needed Crane Required? (1 = yes, 0 = no) Profit If Project Won ($1000) con m in

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Accounting And Financial Management

Authors: Steven J. Peterson

1st Edition

0131109391, 978-0131109391

More Books

Students also viewed these Accounting questions

Question

someexamples of the "Reporting Net vs. Gross Revenue"

Answered: 1 week ago

Question

What steps will Sara need to take to conduct a benefit audit?

Answered: 1 week ago