Problem. The following table gives the data on a project. table [ [ ACTIVITY , DESCRIPTION, table [ [ IMMEDIATE ] , [
Problem. The following table gives the data on a project.
tableACTIVITYDESCRIPTION,tableIMMEDIATEPREDECESSORStableDURATIONWEEKStableTOTAL COSTRSBasic design,IHardware design for Hardware design for BKDrawings for Software specifications,MParts purchase for BParts purchase for I,Drawings for I,Installation drawings,I,QSoftware purchases,Delivery of parts for BDelivery of parts for ASoftware delivery,QAssembly of AAssembly of BWTest Test BVFinal Installation,Final system test,
a Draw the network for this project
b Draw the cost baseline
c The status of the project at the end of the week is as follows:
;
Calculate the SV and CV of the project
d What is the expected cost of completion and duration of the project based on current performance
e What is the expected cost of the project and duration if the efficiency becomes for the remaining period of the project
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started