Question

1 Approved Answer

PROCUREMENT AND CONTRACT MANAGEMENT (CALCULATION) PLEASE ANSWER ONLY IF YOU KNOW THE ANSWER AND CORRECTLY! Complete the empty fields in the following tables which compares

PROCUREMENT AND CONTRACT MANAGEMENT (CALCULATION)

PLEASE ANSWER ONLY IF YOU KNOW THE ANSWER AND CORRECTLY!

Complete the empty fields in the following tables which compares different contract types:

Table 1

Contract Type

Customer Payment

Actual Cost

Profit

Firm Fixed Price

Contracted (Target)

R400 000

R250 000

R150 000

Actual

R

R600 000

R

Actual

R

R150 000

R

Table 2

Contract Type

Customer Payment

Actual Cost

Fee

Cost plus fixed fee contract

Contracted (Target)

R7.25million

R7million

R

Actual

R

R8.75million

R

Actual

R

R4million

R

Table 3

Contract Type

Cost

Customer payment

Contractor Fee

??

Contracted (Target)

R

R5.75 million

R500 000

Contract with 60/40 sharing ratio and guaranteed maximum price (cost ceiling) of R6 million

Actual

R4million

R

R

Actual

R5.5million

R

R

Actual

R6.2million

R

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tidy Finance With R

Authors: Christoph Scheuch, Stefan Voigt, Patrick Weiss

1st Edition

1032389346, 978-1032389349

More Books

Students also viewed these Finance questions

Question

What are the determinants of cash cycle ? Explain

Answered: 1 week ago