Question
PROCUREMENT AND CONTRACT MANAGEMENT (CALCULATION) PLEASE ANSWER ONLY IF YOU KNOW THE ANSWER AND CORRECTLY! Complete the empty fields in the following tables which compares
PROCUREMENT AND CONTRACT MANAGEMENT (CALCULATION)
PLEASE ANSWER ONLY IF YOU KNOW THE ANSWER AND CORRECTLY!
Complete the empty fields in the following tables which compares different contract types:
Table 1
Contract Type | Customer Payment | Actual Cost | Profit | |
Firm Fixed Price | Contracted (Target) | R400 000 | R250 000 | R150 000 |
Actual | R | R600 000 | R | |
Actual | R | R150 000 | R |
Table 2
Contract Type | Customer Payment | Actual Cost | Fee | |
Cost plus fixed fee contract | Contracted (Target) | R7.25million | R7million | R |
Actual | R | R8.75million | R | |
Actual | R | R4million | R |
Table 3
Contract Type | Cost | Customer payment | Contractor Fee | |
?? | Contracted (Target) | R | R5.75 million | R500 000 |
Contract with 60/40 sharing ratio and guaranteed maximum price (cost ceiling) of R6 million | Actual | R4million | R | R |
Actual | R5.5million | R | R | |
Actual | R6.2million | R |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started