Product A is made of Four units of B and two units of C. B is made of three units of D and two E.

Product A is made of Four units of B and two units of C. B is made of three units of D and two E. C is made of two units of F and one unit of E. Lead times for purchase of each unit are: A takes one week, B takes two weeks, C takes one week. D and E take 2 weeks and F takes 3 weeks. Assume that there is a demand for 150 units of A in week 8. There is on-hand inventory of 100 units of B, and 20 units of C. There is a scheduled receipt of E for 500 units in week three. Assume all items are purchased L4L except for item D which is ordered in multiples of 50, F which is ordered in multiples of 200 and E which is 500

A) Show the bill of materials (product structure tree)

B) Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates

image text in transcribed \begin{tabular}{|c|c|c|c|c|c|c|c|c|c|} \hline MRP Worksheet & Week Number & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\ \hline & Quantity & & & & & & & & \\ \hline & & & & & & & & & \\ \hline Item: & Gross requirements & & & & & & & & \\ \hline & Scheduled receipts & & & & & & & & \\ \hline Quantity = & Projected on hand & & & & & & & & \\ \hlineLT= & Net requirements & & & & & & & & \\ \hline Lot Size = & Planned-order receipts & & & & & & & & \\ \hline On hand = & Planned-order releases & & & & & & & & \\ \hline & & & & & & & & & \\ \hline Item: & Gross requirements & & & & & & & & \\ \hline & Scheduled receipts & & & & & & & & \\ \hline Quantity = & Projected on hand & & & & & & & & \\ \hline LT= & Net requirements & & & & & & & & \\ \hline Lot Size = & Planned-order receipts & & & & & & & & \\ \hline On hand = & Planned-order releases & & & & & & & & \\ \hline & & & & & & & & & \\ \hline Item: & Gross requirements & & & & & & & & \\ \hline & Scheduled receipts & & & & & & & & \\ \hline Quantity = & Projected on hand & & & & & & & & \\ \hline LT= & Net requirements & & & & & & & & \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

6th Edition

1398606197, 978-1398606197

More Books

Students also viewed these General Management questions

Question

Define power.

Answered: 1 week ago

Question

Differentiate tan(7x+9x-2.5)

Answered: 1 week ago

Question

Explain the sources of recruitment.

Answered: 1 week ago

Question

Differentiate sin(5x+2)

Answered: 1 week ago

Question

Compute the derivative f(x)=1/ax+bx

Answered: 1 week ago