Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

Production of 2,500 umbrellas during September. Direct Materials (all materials purchased were used): - Standard cost: $4.50 per umbrella - Total actual costs: $10,950 -

Production of 2,500 umbrellas during September.

Direct Materials (all materials purchased were used): - Standard cost: $4.50 per umbrella - Total actual costs: $10,950 - Materials rate variance was $325 favourable

Direct Manufacturing Labour: - Standard cost is 3.2 umbrellas per hour at $20.00 per hour - Actual cost per hour was $20.50 - Labour rate variance was $400 unfavourable

Questions: 1. What is the total direct materials flexible-budget variance? 2. What is the direct material efficiency variance? 3. What is the total actual cost of direct manufacturing labour? 4. What is the labour efficiency variance for direct manufacturing labour? 5. What is the total labour flexible-budget variance?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions