Project #2 Percentage of Completion During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019.
Project #2 Percentage of Completion
During 2017, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2019. The following information is available.
2017
2018
2019
Costs incurred to date
$404,000
$853,160
$1,073,000
Estimated costs to complete
606,000
254,840
0
Billings to date
301,000
904,000
1,580,000
Collections to date
271,000
812,000
1,418,000
Instructions:
- Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
- Prepare all necessary journal entries for 2017, 2018, and 2019.
- Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
- Your work can be completed on 1Excel sheet.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started