Project A: (-2,000, 500, 600, 700, 800) Project B: (-2000, 950, 850, 400, 300) If the discount rate is 12%, what is the discounted payback

Project A: (-2,000, 500, 600, 700, 800) Project B: (-2000, 950, 850, 400, 300) If the discount rate is 12%, what is the discounted payback period for project A, and B?

At what discount rate will we be indifferent between A and B?