Project A cost $1,050 and Project B cost $1,050, there expected net cash inflows are shown on the timeline below and there WACC is 10.00%.
- Project A cost $1,050 and Project B cost $1,050, there expected net cash inflows are shown on the timeline below and there WACC is 10.00%. What is the Discounted Payback for Project A?
-
WACC 10.00%
0 1 2 3 4
l l l l l
ProjA -$1,050 $675 $650
ProjB -$1,050 $360 $360 $360 $360