Project A has an IRR of 23.4%. Project B has an IRR of 33.1%. The firm's cost of capital is 18%. Which project is better,
Project A has an IRR of 23.4%. Project B has an IRR of 33.1%. The firm's cost of capital is 18%. Which project is better, A or B, or can't you tell?
Step by Step Solution
There are 3 Steps involved in it
Step: 1