Question
1 Approved Answer
Project A: IRR = 4%, Initial cost = 100, NPV = 200 Project B: IRR = 14%, Initial cost = 200, NPV = 230 Project
Project A: IRR = 4%, Initial cost = 100, NPV = 200 Project B: IRR = 14%, Initial cost = 200, NPV = 230 Project C: IRR = 6%, Initial cost = 300, NPV = 300 Project D: IRR = 22%, Initial cost = 100, NPV = 260 If you can only choose 1 of the above projects above, which one should you choose? Project A Project B Project C Project D Not enough information to determine which project is preferred