Project A Project B Project C Now -150,000 -300,000 -150,000 End of Year 1 120,000 200,000 110,000 End of year 2 80,000 180,000 90,000 IRR
| Project A | Project B | Project C |
Now | -150,000 | -300,000 | -150,000 |
End of Year 1 | 120,000 | 200,000 | 110,000 |
End of year 2 | 80,000 | 180,000 | 90,000 |
IRR of each project
NPV of each project
If independent, which should be accepted
If mutually exclusive, which should be selected
If budget is 450,000, which should be selected