Question
Project A requires an original investment of $53,800. The project will yield cash flows of $15,600 per year for 4 years. Project B has a
Project A requires an original investment of $53,800. The project will yield cash flows of $15,600 per year for 4 years. Project B has a computed net present value of $4,050 over a 4-year life. Project A could be sold at the end of 4 years for a price of $15,500.
Following is a table for the present value of $1 at compound interest:
Year | 6% | 10% | 12% | |||
1 | 0.943 | 0.909 | 0.893 | |||
2 | 0.890 | 0.826 | 0.797 | |||
3 | 0.840 | 0.751 | 0.712 | |||
4 | 0.792 | 0.683 | 0.636 | |||
5 | 0.747 | 0.621 | 0.567 |
Following is a table for the present value of an annuity of $1 at compound interest:
Year | 6% | 10% | 12% | |||
1 | 0.943 | 0.909 | 0.893 | |||
2 | 1.833 | 1.736 | 1.690 | |||
3 | 2.673 | 2.487 | 2.402 | |||
4 | 3.465 | 3.170 | 3.037 | |||
5 | 4.212 | 3.791 | 3.605 |
Use the tables above.
a. Determine the net present value of Project A over a 4-year life with salvage value assuming a minimum rate of return of 12%. Round your answer to two decimal places. $
b. Which project provides the greatest net present value?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started