Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day
Project ABC
Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and with 50% of work completed $45,000.00 has been spent. Calculate the following and submit the exercise results in a Word document.
Budget at Completion (BAC) = ___________________________ #feet fence * cost/foot
Planned Value (PV) - ________________________________ BAC * (%time passed)
Earned Value (EV) _______________________________________ BAC * % completed
Actual Cost (AC) _________________________________________
Cost Variance (CV) _________________________________________ EV - AC
Schedule Variance (SV) _________________________________________ EV - PV
Cost Performance Index (CPI) ____________________________________ EV/AC %
Schedule Performance Index (SPI) ___________________________________ EV/PV %
Estimate at Completion (EAC) _____________________________________ BAC/CPI
Estimate to Complete (ETC) ____________________________________ EAC - AC
Variance at Completion (VAC) ____________________________________
BAC-EAC To Complete Performance Index ______________________________ (BAC-EV)/(BAC/AC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started