Project B cost $5,000 and will generate after-tax net cash inflows of $500 in year one, $1,200 in year two, $2,000 in year three, $2,500
Project B cost $5,000 and will generate after-tax net cash inflows of $500 in year one, $1,200 in year two, $2,000 in year three, $2,500 in year four, and $2,000 in year five. What is the NPV using 8% as the discount rate? NOTE: Enter amounts rounded to two decimals (e.g., 78.76 or 40.00). Year Net Cash Inflow PV 0 ($ $500 2 $1,200 3 $2,000 4 $2,500 5 $2,000 NPV Total