Project C You are given the following data. Calculate the VAC (Variance at Completion). Project C Budget $3,500,000 Duration 450 Status 80 EV $600,000 PV
Project C
You are given the following data. Calculate the VAC (Variance at Completion). Project C
Budget $3,500,000
Duration 450
Status 80
EV $600,000
PV $580,000
AC $923,000
BAC =
1. Assume future budget estimates do not change
ETC =
EAC =
VAC =
2. Assume future costs continue at the same spending rate
ETC =
EAC =
VAC =
3. Look at the VAC results for Project C. Make a comment or recommendation regarding the ETC, EAC, and VAC.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started