Project Cost NPV A $ 8,000 $ 4,000 B 11,000 7,000 C 9,000 5,000 D 7,000 4,000 Suppose that you could invest in the same
Project | Cost | NPV |
A | $ 8,000 | $ 4,000 |
B | 11,000 | 7,000 |
C | 9,000 | 5,000 |
D | 7,000 | 4,000 |
Suppose that you could invest in the same Projects , and you have only $ 25,000 to invest . Which projects would you choose ? Why ?