Question
Project Crashing Assignment Consider the following project represented by the table of activities and predecessors. Illustrate how this project can be crashed stagewise. What is
Project Crashing Assignment
Consider the following project represented by the table of activities and
predecessors. Illustrate how this project can be crashed stagewise. What is
the minimum time and cost for the crashed project?
Activity Predecessors Time Required Cost
Normal Crash Normal Crash
A - 4 2 10,000 14,000
B A 6 5 30,000 34,500
C A 2 1 8,000 9,500
D B 2 1 12,000 18,000
E B, C 7 5 40,000 52,000
F D, E 6 3 20,000 29,000
Hint:
1) Calculate the critical path and find the critical activities.
2) Apply the rule for choosing activities for crashing (the one with the least
cost slope which is also a critical activity). Crash this activity, i.e., reduce
its duration, calculate the new project completion time and cost of
crashing this stage.
3) For the next stage, continue with crashing with the next available
candidate. (Check if the critical path has changed because of crashing).
4) Indicate the crashed activity, crashed duration, and the stepwise and
the cumulative cost of the crashing in each stage.
In addition, you may assume partial crashing, i.e., reducing an activity's duration
by less than the maximum crashing amount, is permitted for all activities.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started