PROJECT DESCRIPTION A private company in Texas will construct a warehouse facility. It will be a four-hundred-thousand square-foot warehouse. For this scenario, the Present Worth

PROJECT DESCRIPTION

A private company in Texas will construct a warehouse facility. It will be a four-hundred-thousand square-foot warehouse. For this scenario, the Present Worth Analysis must be calculated.

Scenario

The second scenario has a one-phase construction process that lasts 1 year. The civil engineering design will start right away taking a year to complete. The civil engineer is going to be paid 70% of the total fee when land development approvals are accepted (year 1). The other 30% is going to be paid when the site work is completed(year 2). The architectural engineer will design the building at the same time the site work is being constructed. He will be paid 70% of the total fee when the design is completed(year 2) and the other 30% when the construction is completed (year 3).

ASSUMPTIONS

Making a few general assumptions helped to make the calculations and decisions easier and consistent.

1. There will not be trouble finding a tenant as soon as leasing is offered. This eliminates the possibility of not filling the warehouse due to lack of rental interest.
2. All necessary tools and furniture for the space was previously purchased and therefore not included in the calculations.
3. When discussing financing, the interest rate was based on an educated assumption. The assumption was made for a 3% annual rate.

4. The assumption was made that there will be 60 employers working in the facility. This assumption was required for the costs of sewer and water that must be considered.

Scenario

Expenses:

The Civil Engineer gets a $91,000 fee. (70% on year 1) and (30% on year 2).
The site work costs $850,000, to be paid on year 2.
The Architectural Engineer gets a $3,150,000 for the design. (70% on year 2) and (30% on year 3)
The building construction costs $56,000,000 to be paid on year 3.
The pavement rehabilitation costs $150,000 to be paid on years 9, 14,19.
The advertisement for leasing costs $1,300 annually on years 2, 3, and 4.
The landscape maintenance costs $3,500 annually between the years 3 thru 20.
The snow removal costs $1,500 annually between the years 3 thru 20.
The insurance costs $30,000 annually between the years 3 thru 20.
The general building maintenance costs $650,000 annually between the years 3 thru 9, and $1,100,000 between the years 10 thru 20.
The electricity costs $250,000 annually between the years 3 thru 9, and $380,000 between the years 10 thru 20.
The sewer costs $1,500 annually between the years 3thru 9, and $3,000 between 10 thru 20.
The water costs $500 annually between the years 3 thru 9, and $900 between 10 thru 20.
The fire suppression costs $300 annually between the years 3 thru 9, and $500 between 10 thru 20.
The loan payment is $2,380,000 annually between the years 1 thru 20.

Income:

The loan income is a total of $35,000,000 on year 1.
The lease income is $3,000,000 annually between the years 4 thru 9.
The rental income is $2,600,000 annually between the years 10 thru 20.

MAKE SURE TO SUBMIT THE FOLLOWING:

1. ALL WORK MUST BE CLEAR AND FOLLOW A LOGICAL PATTERN
2. INCLUDE THE CASH FLOW
use "discrete cash flow: compound intrest factors" chart online.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Crime And Punishment In The Future Internet

Authors: Sanja Milivojevic

1st Edition

036746800X, 978-0367468002

More Books

Students also viewed these Finance questions

Question

1. Signs and symbols of the map Briefly by box ?

Answered: 1 week ago

Question

Types of physical Maps?

Answered: 1 week ago

Question

Explain Intermediate term financing in detail.

Answered: 1 week ago