Project Gamma started 3 months ago. As of today, planned value of this project is $ 8 0 , 0 0 0 , actual cost

Project Gamma started 3 months ago. As of today, planned value of this project is $80,000, actual cost of this project is $70,000, and earned value of this project is $60,000.
A. What is the cost variance as of today? Show all your work. (.5 pt)
B. What does the cost variance indicate? (.5 pt)
C. What is the schedule variance as of today? Show all your work. (.5pt)
D. What does the schedule variance indicate? (.5 pt)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P Robbins, Mary Coulter

11th Edition

9780273752776, 132163845, 273752774, 978-0132163842

More Books

Students also viewed these General Management questions