Question

1 Approved Answer

project has been assigned a discount rate of 12 percent.If The project starts immediately it will have an initial cost of 480 and cash inflows

project has been assigned a discount rate of 12 percent.If The project starts immediately it will have an initial cost of 480 and cash inflows of 530 a year for three years if the start is delayed two year the initial cost 520 and the cas row will increase 585for four yeas what is the value of the option to wait