PROJECT MANAGEMENT A project manager reviewed a project that was similar to one he is currently working on. He did this to assist him in
PROJECT MANAGEMENT
A project manager reviewed a project that was similar to one he is currently working on. He did this to assist him in costing items for his current project. He made a few adjustments based on the difference in design. What type of budgeting technique did he use?
Group of answer choices
Trend analysis
Specific analogy
Comparison based
Parametric