Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Project Management case study: Managing a 2 - Week Project Recently, I experienced the challenge of having short project, and I mean really short: a

Project Management case study: Managing a 2-Week Project
Recently, I experienced the challenge of having short project, and I mean really short: a 2-week project.
A dramatic re-enactment of that would look like this:
Im called to action. Theres a new project and its got my name all over it. Ive gotten the assignment and Im ready to
really dig into that SoW and prepare for kickoff.
My face shows focus and excitement. Funny... someone must have gotten the dates wrong the project starts tomorrow
and runs for only two weeks. That cant be right. Is that right? Now my face shows confusion and fear. Messages go out
via all known communication methods. Confirmation. It is right.
Project Details
We had been hired to create functional prototypes for a user testing engagement. There was a finite date for this testing
and it was quickly approaching. The prototypes have to take into account about six different flows and countless use
cases. Like the delivery date, the budget was also fixed and finite we had to do some fancy number games to get the
right team composition to ensure the success of the project.
QUICK FACTS
- Type of Client Company: Home appliance
- Type of project: Prototyping for user testing
- Cost or cost range: $20,000 $50,000
- Timeline: 2-3 weeks
- Team size: 5
- Methodology: N/A
- Main goal: Accomplish prototyping to client specifications prior to user panel testing date
- Main challenge: Getting assets needed from the client to turn around a timely prototype
So What Now?
Decisions need to be made around what stays and what goes from your normal project checklist. The team is quickly on
boarded and the internal expectations are shaped around the unexpected and unyielding demands of a two-week project.
Project managers face all kinds of surprises, and each one comes with a special flavour all its own. Theyre seasoned
with Stay in Scope and Budget,Produce the Deliverable and Unify the Team.
On a normal project, these things are par for the course and something we are all trained to do using our charismatic PM
ways. But this is no normal project. Condensing a full cadence of ceremonies and processes into a two week period is
simply not going to happen without a magic wand.
I havent seen any of those in my office, but by all means, if you have one, use it.
Assuming, like me, that you are without magical resources, a real problem has been presented to you and you must find
a solutionlike, yesterday. The most helpful thing to do is start with a basic list of questions to help you navigate the best
path to achieving the deliverable on such a short deadline.
2-Week Project Tips: How to Manage A Short Project
Here are the 5 questions I recommend starting with (and the answers as they pertained to my project):
1. Who comprises my team and are they armed with the tools and assets they need to at least begin work?
Given the parameters, we ended up with a team comprised of a Delivery Director, a Project Manager, an Architect and
two offshore Developers. We were relying heavily on the provision of assets to base design on and this became a bit of a
blocker at one point, resulting in the addition of another developer for a day or two.
2. What meetings are crucial (daily standups, demos, etc.) and what can be disregarded (retros, grooming, etc.)?
We decided that daily stand ups with the client and demos were the two essentials for a project this short. Namely
because the key here is staying aligned and on time. Failing at one of those would jeopardize the success of the whole
project.
3. Does your team and your client have a thorough understanding of what is being developed and delivered? Is there
complete alignment?
Thanks to the meetings mentioned, our continued touchpoints ensure alignment through delivery.
4. What does the full timeline of this project look like? When are check-in points, QA, revisions...?
The timeline was established going into it but had to remain very flexible. There were quite a few last minute lets jump
on a call meetings to clarify issues and defects that arose during development.
5. Does this lead to another SOW that expands on this portion?
In our case, it doesnt, but more similar work will be granted to us in the future as these prototypes are needed.
Answering these questions, as I did above, will give you a good starting point to guide the following weeks of work.
Unfortunately, with a project this short, some of the typical discovery items youd research during kick-off are going to be
revealed along the way, parallel to development.
HELPFUL TIPS
At the very start of the project, establish a real-time method of communication with the client. This type of deadline
will require immediate response to questions and the standard respectable delay will not suffice. Slack, Hipchat or Gchat
or all good options (check out this article for other communication tools).
It will be very important to allow key player

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

THE Classroom Management Book

Authors: Harry K. Wong, Rosemary T. Wong, Sarah F. Jondahl, Oretha F. Ferguson

1st Edition

9780976423331

More Books

Students also viewed these General Management questions

Question

Draw a picture consisting parts of monocot leaf

Answered: 1 week ago