Project manager Peter is currently executing a new phone system installation project. The project has a budget of $3,000 and a duration of 11
Project manager Peter is currently executing a new phone system installation project. The project has a budget of $3,000 and a duration of 11 months total. Peter just completed the 8th month of the project. The project team has completed 90% of the project work and has spent $2,900. Summary: Budget:. Duration: Now:. Completed: Total Spent: CV: EAC : Find the following values: (0.5 point each) BAC : PV: CPI : ETC : Summary: Budget:. Duration:. completed Completed:. Total Spent:.. 90% $3,000 11 months Find the following values: BAC : PV: CPI : ETC : CV: EAC : 8th month completed $2,900 Based on the above values, comment on the project status EV : SV: VAC : 2. (7.5 point) Project manager Mary is currently executing a network upgrade project. The project has a budget of $4,000 and a duration of 4 years total. Mary just completed the 17th month of the project. The project team has completed 35% of the project work and has spent $1,500. $4,000 4 Years Now:. ... 35% $1,500 (0.5 point each) EV: SV: VAC: AC: SPI : TCPI : Based on the above values, comment on the project status AC: SPI : TCPI : 17th month
Step by Step Solution
★★★★★
3.45 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
1 For phone system installation project PV Planned Value BAC x of work scheduled to be completed at this point PV 3000 x 90 2700 EV Earned Value BAC x of work actually completed at this point EV 3000 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started