Project managers utilize make or buy analysis frequently during a project.After you identified a risk for an activity, you estimated that an additional $5.000 may
Project managers utilize "make or buy analysis" frequently during a project.After you identified a risk for an activity, you estimated that an additional $5.000 may be required if this risk occurs. Therefore, you included this fund in your cost baseline. How do we name this fund in project cost management? A. Emergency reserve B. Fallback reserve C. Contingency reserve D. Management reserve
Step by Step Solution
There are 3 Steps involved in it
Step: 1