Project Network Rules for Activity on Node diagrams include all of the following EXCEPT: Networks typically flow from left to right. Looping is not allowed.
Project Network Rules for Activity on Node diagrams include all of the following EXCEPT:
Networks typically flow from left to right.
Looping is not allowed.
Conditional statements are allowed.
Identify each activity with a unique identifier; this identifier must increment ABC etc. as the network proceeds.