Question

00
1 Approved Answer

Project Objectives: [List project objective] Operational Step Responsible Person Timeline [List project objective] Operational Step Responsible Person Timeline [List project objective] Operational Step Responsible Person

Project Objectives:

  • [List project objective]
Operational Step Responsible Person Timeline
  • [List project objective]
Operational Step Responsible Person Timeline
  • [List project objective]
Operational Step Responsible Person Timeline

The selected organization is starbucks

A project plan is based on research and organizational goals.To seean exemplar project plan, review the Project Plan Example.

Use the Project Plan Template and the business needs identified in your Week 3 Balanced Scorecard to:

Develop the project objectives.

Explain what operational steps will be taken to achieve your stated objectives.

Identify the responsible person(s) for eachoperational step.

Outline a timeline for each operational step.

Justify the choices you made in your project plan in a 525-to700word response on the Project Plan Template. For "Responsible Person" (on the template) identify the functional department or functional position within the organization. You do not have to have the person's actual name.

Example

Project Objectives

Identify the top three potential customer groups for this opportunity and describe their characteristics and preferences.

Operational Step Responsible Person Timeline
Review the organization's customer database to determine potential customer groups Leo (Market Research Manager) 9/30 (1 week)
Identify the top 3 groups to target based on volume, brand loyalty, and location Betty (Director of Marketing) 10/7 (2 weeks)
Survey customers regarding food preferences and potential menu items Tom (Customer Service Representative) 10/21 (4 weeks)
Share customer feedback with inventory and operational teams Betty/Tom 10/28 (5 weeks)

Determine the top 5 locations and times to completea pilot study with your test market.

Operational Step Responsible Person Timeline
Review sales data to determine peak sales opportunities by location Jim (Director of Sales) 9/30 (1 week)
Identify the top 5 locations in which to conduct the desert taco pilot Jim 10/7 (2 weeks)
Create marketing collateral and social media communications to promote the desert taco pilot Oliver (Media Relations Manager) 10/21 (4 weeks)
Provide expected volume and product information for the inventory team Jim 10/7 (2 weeks)

Estimate the required inventory and supply chain needs necessary to support the desert taco pilot.

Operational Step Responsible Person Timeline
Based on expected customer volume, locations, and times, determine the product inventory required to support the pilot. Louise (Controller) 10/14 (3 weeks)
Source supply companies and obtain product pricing quotes and delivery timelines. Louise 10/21 (4 weeks)
Determine shipment and storage needs to support the pilot. Louise and Ben (Operations Manager) 10/21 (4 weeks)
Purchase product for the pilot and arrange transportation to support the desert taco pilot at the various locations. Louise 10/28 (5 weeks)

kindly answer correctly other do not answer

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Probability And Statistics For Engineering And The Sciences

Authors: Jay L. Devore

9th Edition

1305251806, 978-1305251809

Students also viewed these General Management questions

Question

=+b) In which graph is a larger value of a used?

Answered: 1 week ago