PROJECT PERFORMANCE ANALYSIS Highway Project Task: Build 6 0 miles of highway over a period of one year. Budget Data: 5 miles per month at

PROJECT PERFORMANCE
ANALYSIS
Highway Project
Task:
Build 60 miles of highway over a period of one year.
Budget Data:
5 miles per month at $500,000 per mile.
Assumptions:
Planned linear accomplishment of work.
All work is measurable except Program Management/Support, which is LOE.
No work in process at end of month.
Latest Performance Reports:
See the Monthly Performance Data Table and Integrated Program Management Report (IPMR) for
Month 7 that follow this page.
Calculate the:
Schedule Variance Percentage (SV%)
Cost Variance Percentage (CV%)
Cost Performance Index - Efficiency )E
Cost Performance Index - Productivity )P
Schedule Performance Index (SPI)
Months ahead or behind schedule
Percent Complete
Percent Spent
To Complete Performance Index (TCPI)
Independent Estimate at Completion (IEAC)
Estimated Completion Date (in months)(ECD)
Average Performance Rate Required to achieve the ECD
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

BPR always involves automation. Group of answer choices True False

Answered: 1 week ago