Question
Project Resource and Procurement Management Read the case study below and answer ALL the questions that follow. Case Study: Critical Chain Project Management Method Applied
Project Resource and Procurement Management
Read the case study below and answer ALL the questions that follow.
Case Study: Critical Chain Project Management Method Applied to a Multi-project System
Although techniques developed in the 1950sincluding the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT)are usually applied to time management in projects, projects still fail to achieve their time goals. In 1997, Eliyahu Goldratt proposed a method based on the fundamentals of the Theory of Constraints (TOC) called critical chain project management (CCPM) to minimize the inefficiencies identified in traditional project management methodology. The proposed method was accepted by the project management community as a viable alternative that could bring real gains.
The method has some issues that should be considered regarding its implementation when using the CCPM method in a multi-project environment (Lechler, Ronen, & Stohr, 2005 Raz, Barnes, & Dvir, 2004). A multiproject environment is the formation of a network of projects of varying sizes and importance that depend on the same set of resources and are characterized by high uncertainty and high complexity. In these environments, managers are exposed, along with their staff members, to constant changes throughout the project life cycle (Milos?evic & Patanakul, 2002). Organizations that deal with multiple projects simultaneously are often accused of failures in the time management of activities (Wei-Xin, Xu, Xianlong, & Lei, 2013).
Critical Chain is a project management method that focuses primarily on the management of the duration of activities, considering the allocation of resources, and is based on the principles of the Theory of Constraints (TOC). This method was initially proposed by Goldratt (1997) and later detailed by others (Blackstone, Cox, & Schleier, 2009 Leach, 2000 Peng & Jin, 2009 Steyn, 2000).
To perform any activity in a project, two things are necessary: the activity input from a predecessor and a resource to perform the activity thus, the critical chain method includes both resource and activity logic constraints to complete the project on time or earlier. For Leach (2000), the evident constraint of a unique project is the chain of activities that takes the longest to complete. In environments with multiple projects, assuming these projects are carried out at the same time, the resources (people) are typically divided between the projects leading to multitasking, thus reducing the possibility of finishing the activities in the time scheduled. Evidently, at least one of these resources should be the capacity constraint of the system, so the company's resource constraint (people) becomes the drum for scheduling multiple projects.
Since its proposal, the CCPM method has been accepted by part of the project management community, as evidenced in work published by Rand (2000) Umble and Umble (2000) Newbold (2008), Tian, Zhang, and Peng (2010) and Butler and Richardson (2011). These authors advocate the application of the CCPM method as a way to present concepts they consider innovative: a reduction of the initial time estimates to avoid the appearance of the student syndrome and Parkinson's law, by using time buffers at the end of the project and providing ways to address uncertainty in activity planning. In addition, resource bottlenecks as system constraints and managing the project through the indicators of its time consumption should be taken into consideration. These considerations will provide a vision of the entire system, not only focusing on each activity individually, but on the progress of the project as a whole.
Acceptance of the CCPM method by the project management community was evidenced by the fact that it was included in the third edition of the PMBOK Guide (PMI, 2004) and continues to be cited within the Develop Schedule process as a schedule network analysis technique in the Project Time Management processes in the fifth edition of the PMBOK Guide (PMI, 2013).
Furthermore, there is another part of the scientific community that has questioned its basis and application, as can be seen in the work published by Herroelen, Leus, and Demeulemeester (2002) Raz et al. (2004) Herroelen and Leus (2005) and Lechler et al. (2005). These researchers argue that the concepts considered to be innovative are not totally new because they were obtained from concepts or theories formulated earlier and that more empirical evidence and scientific studies are needed to demonstrate the efficacy of the CCPM method.
In the literature reviewed, it was found that most of the work focuses on the analysis of the unique aspects of the CCPM method, such as time buffers (Bie, Cui, & Zhang, 2012 Peng, Junwen, & Huating, 2007 Tukel, Rom, & Eksioglu, 2006) and the application to individual projects (Balakrishnan, 2010 Long & Ohsato, 2008 Peng & Jin, 2009). These publications have made important contributions to the development of the CCPM method, but they have not shown applications in a real multi-project environment nor have they identified the key factors that may affect the performance of the critical chain project management method.
Source: https://journals.sagepub.com/doi/abs/10.1177/8756972819832203
Question 1 (25 Marks)
Why, if there is a tendency to overestimate activity durations and add in a safety net to the end of a project, do so many "projects still fail to achieve their time goals" and come in behind schedule? Reinforce the explanations that Critical-Chain Project Management (CCPM) offers in the case study and outside of the case study.
Comments:
- All required elements must be met and exceeded - a critical discussion of FIVE (5) of the reasons presented
- At least 2 of the 5 reasons listed should be from the case study.
- Unique & original arguments presented
- Current and credible sources successfully integrated to support arguments
Question 2 (25 Marks)
With reference to the case study, elaborate on the benefits of applying the CCPM methodology.
Comments:
- Cited arguments must be well paraphrased
- Theories, concepts and models critically evaluated to support answer.
- Innovation in integrating examples with relevant theory, concepts and models
- Current and credible sources successfully integrated to support arguments
- All references use Harvard Method
- Current and credible sources successfully integrated to support arguments
Question 3 (25 Marks)
Critically discuss what is meant by Goldratt's critical chain as referred to in the case study, and how effective it is in scheduling resource constrained projects. Present examples to illustrate points crafted in the discussion.
Comments:
- All required elements met and exceeded
- A critical discussion of at least FIVE (5) benefits presented
- Unique & original arguments presented
- Cited arguments are well paraphrased
- Current and credible sources successfully integrated to support arguments
- All references use Harvard Method
Question 4 (25 Marks)
Rationalise why Critical Chain Project Management recommends the use of buffers and state each type of buffer's specific purpose.
Comments:
- All required elements met and exceeded
- A critical discussion of at least FIVE (5) benefits presented
- Unique & original arguments presented
- Cited arguments are well paraphrased
- Current and credible sources successfully integrated to support arguments
- All references use Harvard Method
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started