Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,500 per year for 5 years. Project L costs
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,500 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $8,000 per year for 5 years.
Calculate the two projects' NPVs, assuming a cost of capital of 14%. Do not round intermediate calculations. Round your answers to the nearest cent.
Project S: $
Project L: $
Which project would be selected, assuming they are mutually exclusive?
Based on the NPV values, -Select-Project SProject LItem 3 would be selected.
Calculate the two projects' IRRs. Do not round intermediate calculations. Round your answers to two decimal places.
Project S: %
Project L: %
Which project would be selected, assuming they are mutually exclusive?
Based on the IRR values, -Select-Project SProject LItem 6 would be selected.
Calculate the two projects' MIRRs, assuming a cost of capital of 14%. Do not round intermediate calculations. Round your answers to two decimal places.
Project S: %
Project L: %
Which project would be selected, assuming they are mutually exclusive?
Based on the MIRR values, -Select-Project SProject LItem 9 would be selected.
Calculate the two projects' PIs, assuming a cost of capital of 14%. Do not round intermediate calculations. Round your answers to three decimal places.
Project S:
Project L:
Which project would be selected, assuming they are mutually exclusive?
Based on the PI values, -Select-Project SProject LItem 12 would be selected.
Which project should actually be selected?
-Select-Project SProject LItem 13 should actually be selected.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started