Project Scheduling with Uncertain Time: A B C D E LL Start F G H A activity Immediate Time (weeks) Most predecessor Optimistic A
Project Scheduling with Uncertain Time: A B C D E LL Start F G H A activity Immediate Time (weeks) Most predecessor Optimistic A A A C, D B, C E, F F, G B 2 6 3 4 .5 3 2 3 C D 5 7 6 5 3 6 14 F Probable Pessimistic 5 E 8 11 10 11 7 10 7 19 H Finish Be sure to round the expected time to one decimal place. Be sure to round the variance and standard deviation to 2 decimal places. Solve the problem and enter your answers to the questions: 1. What are the critical path activities? 2. What is the expected completion time for the project (#of weeks)? (Your answers need to be within 0.1 of the correct answer) 3. What are the variance and standard deviation for the critical path? (Your answers need to be within 0.1 of the correct answers) 4. What is the probability that the project can be completed in less than 28 weeks? (Round your probability to 3 decimal places.) Be sure to enter your answers as follow: For (1): show the sequence of critical path activities letters. For (2): show the answer is # of weeks.
Step by Step Solution
★★★★★
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
Project Scheduling Analysis Critical Path The critical path consists of the activities with the leas...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started