Project scope statement (effectively detailing the scope using also images) for a kitchen renovation, which project charter is as follow 4. Project Scope Statement Project

Project scope statement (effectively detailing the scope using also images) for a kitchen renovation, which project charter is as follow

4. Project Scope Statement
Project Purpose / Business JustificationDescribe the business need this project addresses.

The family's current kitchen located in Downtown Vancouver, BC with an approximately area of 300 square feet, is outdated and inadequate for their purposes. So this project aims to renovate the kitchen for the family of 4, to improve their quality of life, functionality, and aesthetic of the space. This project addresses the family's requirement for a more modern and efficient kitchen space for their daily activities. The market value of the house will rise as a consequence of the renovations.

Objectives (in business terms)Describe the measurable outcomes of the project, e.g., reduce cost by xxxx or increase quality to you

Improve kitchen functionality by 50% by utilizing modern appliances and efficient layouts

Make the kitchen more aesthetically pleasing according to the preferences of the family and 25% energy efficiency

Increase the overall value of the house by renovating the kitchen

Finish the project within the $60,000 budget

Finish the project within the proposed timeline

DeliverablesList the high-level "products" to be created (e.g., improved xx process, employee manual on yyyy)

1-Kitchen design plan

2-Updated and enhanced plumbing and electrical system

3-Appliances that require less energy

4-Remodeled floor and countertops

5-New coat of paint for the kitchen

6-Installation of the Kitchen

6-Last clean up

...

ScopeList what the project will and will not address (e.g., this project addresses units that report to the Office of Executive Vice President. Units that report to the Provost Office are omitted)

Demolition of existing structures within the kitchen

Installation of new flooring and painting

Installation of customized cabinetry and countertops

Overhaul of existing plumbing and electrical systems to modern standards.

Installation of energy efficient appliances.

Final clean up and finishing touches.

Exclusions:

No modifications will be made outside of the kitchen area.

This project will not involve structural changes to the property.

Project MilestonesPropose start and end dates for Project Phases (e.g., Inception, Planning, Construction, Delivery) and other major milestones.

Overall project duration (13 weeks): July 01, 2024 to September 29, 2024

  1. Initiating phase 2 weeks starting July 01, 2024. Ending July14, 2024.
  2. Planning phase 2 weeks starting July 15, 2024. Ending July 28, 2024.
  3. Permitting phase 1 week starting starting July 29, 2024. Ending August 04, 2024.
  4. Construction phase 6 weeks starting August 05, 2024. Ending September 15, 2024.
  5. Inspection phase 1 week starting September 16, 2024. Ending September 22, 2024.
  6. Delivery phase 1 week starting September 23, 2024. Ending September 29, 2024

Budget

This project has a budget of $60,000, including $5,000 for unexpected costs

Design 3% - $1,800

Permit costs 2% - $1,200

Demolition and disposal 10% - $6,000

Electrical and plumbing 20% - $12,000

Cabinetry 20% - $12,000

Flooring 10% - $6,000

Countertops 10% - $6,000

Appliances 15% - $9,000

Painting and final touches 1.6%% - $1,000

Contingency "(unexpected costs) 8.33% - $5,000

Total 100% - $60,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Leading And Collaborating In A Competitive World

Authors: Thomas S Bateman, Scott A Snell, Robert Konopaske

15th International Edition

978-1265051303

More Books

Students also viewed these General Management questions

Question

Explain the elements necessary to show false imprisonment.

Answered: 1 week ago

Question

c. What type of degree does it offer?

Answered: 1 week ago