Project Scope Statement Template Project name: Second Venue Expansion Project Prepared by: Simonetta Date: 13/06/2023 Project Objectives The high-level goals of the project are to

Project Scope Statement Template

Project name: Second Venue Expansion Project

Prepared by: Simonetta

Date: 13/06/2023

Project Objectives

The high-level goals of the project are to open a second venue for the restaurant in another city, thereby expanding the customer base, increasing brand presence, and generating additional revenue. The success criteria for the project include:

  1. Opening the second venue within a timeline of six months from the project start.
  2. Increasing the customer base by 30% within the first year of the second venue's operation.
  3. Achieving a positive return on investment within two years of the second venue's operation.

Product Scope Description

The project involves opening a new restaurant venue in another city. The venue should replicate the brand and concept of the existing restaurant while catering to the specific requirements and preferences of the target market in the new city. The scope includes but is not limited to:

  1. Location scouting and selection of a suitable site.
  2. Renovation and interior design of the new venue.
  3. Equipment procurement and installation.
  4. Hiring and training of staff for the second venue.
  5. Marketing and promotional activities to introduce the new venue to the target market.

Acceptance Criteria

The acceptance of the project deliverables will be based on the following criteria:

  1. The second venue is successfully opened within the designated timeline of six months.
  2. The new venue is operational and fully equipped with all necessary facilities and equipment.
  3. The staff for the second venue is hired, trained, and ready to provide high-quality service.
  4. The marketing and promotional activities effectively introduce the new venue to the target market and generate customer interest.

Stakeholder Register Template

Project manager

Simonetta

Project phase

Execution

Name

Role

Contact

Category / Level of Authority

Interest

Influence

Expectations

Communication Requirements

Simonetta

Project manager

Email

High/decision maker

Successful second venue opening

Regular project updates and key decisions

Fabio

Project coordinator

Email

Medium/coordinator

Smooth meeting facilitation

Timely meeting updates and agenda distribution

Andrea

Documentation

Email

Low/supportive

Accurate meeting notes and documentation

Meeting minutes sharing and availability

Attilio

Business Development

Email

Low/contributor

New business opportunities

Relevant updates and involvement in decision-making processes

Alisha

Marketing

Email

Low/contributor

Increased brand presence

Marketing-related updates and involvement

Giordan

Resource allocation

Email

Low/contributor

Effective resource management

Resource-related updates and involvement

Gabriel

Budget management

Email

Low/contributor

Cost-effective project execution

Budget-related updates and involvement

Work break down structure (WBS)

Tasks as below

Task Description

Cost Estimate

Duration

Target Date

Project Initiation

$10,000

5 days

15/06/2023

Define project scope and objectives

$2,000

1 day

10/06/2023

Identify project stakeholders

$1,000

1 day

11/06/2023

Develop project charter

$3,000

2 days

12/06/2023

Obtain project authority approval

$4,000

1 day

15/06/2023

Location Selection and Lease Agreement

$50,000

30 days

30/06/2023

Research potential locations

$5,000

5 days

17/06/2023

Visit and evaluate potential locations

$10,000

10 days

28/06/2023

Negotiate lease agreement

$35,000

15 days

30/06/2023

Venue Renovation and Interior Design

$200,000

60 days

30/09/2023

Finish to fill the template for Project Charter with the information already given above.

Project Charter Template

LOMBRA

Project Charter

Second Venue Expansion Project

Project Specifics

Project sponsor

RestoPlus

Project manager

Simonetta

Project organisation

Lombra

Author

Simonetta

Version No.

1

Date Published

15/06/2023

Project authority to proceed

Project sponsor

Name

Restoplus

Signature

Simone

Date

15/06/2023

Project manager

Name

Simonetta

Signature

Simone

Date

15/06/2023

Details

image text in transcribedimage text in transcribedimage text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Everything Stress Management Book

Authors: Eve Adamson

1st Edition

9781580625784

More Books

Students also viewed these General Management questions

Question

Discuss how to use job evaluation to build job structures.

Answered: 1 week ago

Question

Discuss why unions exist.

Answered: 1 week ago

Question

Discuss the alternative types of health care plans.

Answered: 1 week ago