Question
Project SubAccount BCAC, ACWP ,BQAC, AQWP, Percentage complete (%), BCWS . A, 50,00 15,00 6,00 3,00 25% 15,00 B1 80,00 30,00 5,00 4,00 70% 60,00
Project SubAccount BCAC, ACWP ,BQAC, AQWP, Percentage complete (%), BCWS .
A, 50,00 15,00 6,00 3,00 25% 15,00
B1 80,00 30,00 5,00 4,00 70% 60,00
B2 60,00 25,00 4,00 3,00 40% 30,00
Calculate the following values, rounding to 2 decimals:
2.1. Cost variance (CV) (3) A CV =? B1 CV =? B2 CV =?
2.2. Schedule variance (SV) (3) A SV =? B1 SV =? B2 SV =?
2.3. Schedule performance index (SPI) (3) A SPI =? B1 SPI =? B2 SPI =?
2.4. Forecasted cost at completion (FCAC) for each account (Method 1) (4) A - FCAC =? B1 FCAC =? B2 FCAC =? Method 1 total forecasted cost at completion of Phase 1 = ? 2.5. Forecasted cost at completion (FCAC) for each account (Method 2) (4) A - FCAC =? B1 - FCAC=? B2 - FCAC=? Method 2 total forecasted cost at completion (FCAC) of Phase 1 = ?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started