Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely
- Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below:
- 120 total units were planned to be produced
- 130 units have actually been produced
- The financial manager reported that the business had actually spent $13,000 on the project by the end of week three.
- Quantify cost variance. Is the project ahead or behind budget?
Answer the following questions; show all work:
- Quantify schedule variance. Is the project ahead or behind schedule?
- Quantify cost performance efficiency. Is the project performing better or worse than planned?
- Quantify schedule performance efficiency. Is the project performing better or worse than planned?
- What is the forecast of project cost at completion assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?
- What is the forecast of funding needed to complete the project (from this point forward)?
- What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?
- As the project financial manager, what recommendations would you make?
- Proust Manufacturing Co. produces personal fitness machines. The once successful line is no longer selling well, so the company is considering production of a new improved cardio-vascular machine. This can be done by buying needed production equipment. The after tax cash flow for buying this equipment is $700,000, at the beginning of Year 0. The alternative to produce the same output, is tolease that same equipment through four equal payments of $185,000 each year paid at the beginning of the year. The required rate of return (hurdle rate) for this business is 12 percent. Assume no taxes. Revenue from sales of the new cardiovascular machines is expected to be:
- Year 1 - $375,000
- Year 2 - $250,000
- Year 3 - $140,000
- Year 4 - $75,000
Calculate the net present value of both the new purchase option and the lease option. Show all work. Determine the best option for Proust and justify your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started