Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Project UMUC is to produce 310 widgets and is scheduled to take five weeks. Each unit is planned to cost $83. The project is severely

Project UMUC is to produce 310 widgets and is scheduled to take five weeks. Each unit is planned to cost $83. The project is severely cost constrained; the project budget does not include any contingency or management reserves. Performance data for the project at the end of week four is presented below:

247 total units were planned to be produced

271 units have actually been produced

The financial manager reported that the business had actually spent $23,655 on the project by the end of week four.

You calculate, PV, EV, and BAC as follows:

PV = 247 units X $83 per unit = $20,501

EV = 271 units X $83 per unit = $22,493

BAC = 310 units x $83 per unit = $25,730

1.Calculate cost variance (CV). Based on this information, is the project over or under budget? Explain.

2.Calculate schedule variance (SV). Based on this information, is the project ahead or behind schedule? Explain.

3.Calculate cost performance efficiency to three digits. Based on this information, is the project performing better or worse than planned? Explain.

4.Calculate schedule performance efficiency to three digits. Based on this information, is the project performing better or worse than planned? Explain.

5.What is the forecast of project cost at completion assuming remaining work will be performed according to plan? How much budget variance is expected at completion?

6.Assuming remaining work will be performed according to plan, what is the forecast of funding needed to complete the project (from this point forward)?

7.What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mathematical Statistics With Applications In R

Authors: Chris P. Tsokos, K.M. Ramachandran

2nd Edition

124171133, 978-0124171138

Students also viewed these Accounting questions

Question

Define critical thinking and list its seven standards.

Answered: 1 week ago

Question

what is a write-down?

Answered: 1 week ago