Project X Initial Outlay $8,610 Year 1 $3,190 Year 2 $3,290 Year 3 $3,750 Year 4 $7,470 Find the Payback period for the following project:
Project X | |
Initial Outlay | $8,610 |
Year 1 | $3,190 |
Year 2 | $3,290 |
Year 3 | $3,750 |
Year 4 | $7,470 |
Find the Payback period for the following project: The answer should be calculated to two decimal places.