Question

1 Approved Answer

Project:Construction of anewofficebuildinginParramatta Scope:Constructionofa10-storyofficebuildingwithatotalfloorarea of20,000square meters Schedule:The projectisexpectedtotake18monthstocomplete, withaplannedstartdate of January 1st 2023 and a planned end date of June 30th 2024. Budget:Thetotalbudgetfortheprojectis$50million. Assumptions: Theprojectwill

Project:Construction of anewofficebuildinginParramatta

Scope:Constructionofa10-storyofficebuildingwithatotalfloorarea of20,000square meters

Schedule:The projectisexpectedtotake18monthstocomplete, withaplannedstartdate of January 1st 2023 and a planned end date of June 30th 2024.

Budget:Thetotalbudgetfortheprojectis$50million. Assumptions:

Theprojectwill bedividedinto6phases, eachtaking 3monthstocomplete.

Tasks 1:

Theprojectmanagerwilluseearnedvaluemanagement(EVM)totracktheproject's progress.

Question1.1:UseEVMtotracktheproject'sprogressandcalculatethefollowingmetrics (table 1):

  • Plannedvalue(PV)
  • Earnedvalue(EV)-calculatebasedonthe%completion
  • Actualcost(AC)-makereasonableassumptionoftheactual cost yourself
  • Schedulevariance (SV)
  • Costvariance(CV)
  • Scheduleperformanceindex(SPI)
  • Costperformanceindex(CPI)

Question1.2:AnalysetheEVMdatatoidentifyanyscheduleorcostvariances, and recommend corrective actions if necessary.

Table1:EVManalysis

Variance

Performance Index

WBS

Element

March

June

Sep

Dec

March

June

Budget (PV)

%

completion

Earned Value(EV)

Actual Cost (AC)

ScheduleSV

CostCV

ScheduleSPI

CostCPI

1.

Initiation

2,000,000

100%

2,500,000

2.

Planning

4,600,000

85%

3.Design

2,400,000

80%

4. building construction

40,000,000

75%

5.testingand commisioning

920,000

80%

4.occupancyand maintenance

80,000

85%

Totals

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management With CompTIA Project+

Authors: Joseph Phillips

4th Edition

9781259860300

More Books

Students also viewed these General Management questions

Question

1. Explain the benefits of business travel and business events.

Answered: 1 week ago

Question

Define Decision making

Answered: 1 week ago

Question

What are the major social responsibilities of business managers ?

Answered: 1 week ago

Question

What are the skills of management ?

Answered: 1 week ago

Question

Why should an employer be concerned about negligent hiring?

Answered: 1 week ago

Question

What are the various methods of interviewing? Define each.

Answered: 1 week ago