Pronghorn Construction Company began work on a $419,400construction contract in 2017. During 2017, Pronghorn incurred costs of $280,200, billed its customer for $216,300, and collected

Pronghorn Construction Company began work on a $419,400construction contract in 2017. During 2017, Pronghorn incurred costs of $280,200, billed its customer for $216,300, and collected $174,500. At December 31, 2017, the estimated additional costs to complete the project total $161,600.

Prepare Pronghorn's journal entry to record profit or loss, if any, using (a) the percentage-of-completion method

Debit Credit

Construction Expenses

Construction in Process

Revenue from Long-Term Contracts

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions