Question

1 Approved Answer

Proyek B Estimasi Waktu (Minggu) No. Aktifitas Predecessors Waktu Waktu Waktu Optimis (a) Normal (m) Pesimis (b) 1 A 15 18 2 B A 13

image text in transcribed
image text in transcribed
Proyek B Estimasi Waktu (Minggu) No. Aktifitas Predecessors Waktu Waktu Waktu Optimis (a) Normal (m) Pesimis (b) 1 A 15 18 2 B A 13 16 20 3 C A 16 22 24 D A 16 18 21 5 E B.C 15 17 19 6 F D.E 14 18 22 G D.F 10 13 15 H B,F 17 19 22 9 T F,G,H 20 24 28 Pertanyaan : a. Buat Network Planningnya b. Hitung EET nya berdasarkan waktu "NORMAL" c. Tentukan jalur dan jalur kritisnya d. Hitung Expected Time (te) e. Hitung Variance (vt) f. Hitung Standard Deviasi (St)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Economics Of The Energy Industries

Authors: William Peirce

2nd Edition

0275956261, 9780275956264

More Books

Students also viewed these General Management questions

Question

Write a note on transfer policy.

Answered: 1 week ago

Question

Discuss about training and development in India?

Answered: 1 week ago

Question

Explain the various techniques of training and development.

Answered: 1 week ago

Question

Explain the various techniques of Management Development.

Answered: 1 week ago