Question
1 Approved Answer
PV for task E is 300 as per the given project baseline table, project work completed $300 at the end of period 8. At the
PV for task E is 300 as per the given project baseline table, project work completed $300 at the end of period 8. At the end of period 8, the project is ahead of schedule and under budget because SV and CV are positive
Step by Step Solution
There are 3 Steps involved in it
Step: 1