Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

PV vs BAC How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have a scheduled project activity with a total duration of 12

PV vs BAC

How does Planned Value (PV) differ from Budget-at-Completion (BAC)? Suppose you have a scheduled project activity with a total duration of 12 weeks and an activity budget of $1,200. Assuming the planned expenditure rate is constant throughout the activity duration, what is PV at the end of the fourth week? At the end of the tenth week? At the end of the twelfth week?

Suppose now the planned expenditure rate is: $50 for each of the 1st two weeks; $100 for each of the 3rd and 4th weeks; $125 for each of the 5th and 6th weeks; $150 for each of the 7th and 8th weeks; $125 for week 9; and $75 for each of weeks 10 through 12. What is PV at the end of the fourth week? At the end of the tenth week? At the end of the twelfth week?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions