Q 1 . A 1 2 - month long project with 6 0 evenly spread milestones started on 1 st Sept. 2 0 1 9

Q1. A 12-month long project with 60 evenly spread milestones started on 1st Sept. 2019. The project cost was Rs 80 million. Today is 1st March 2020,35 milestones have been completed and Rs 26 million paid to the contractor. What is the PV and EV as of today?